The following are background documents
related to the Request for Qualifications and Proposals (RFQ/P) process
that the City of Tacoma began on Oct. 11, 2005, to find a suitable
vendor to manage the City's performing arts facilities - the Pantages
Theater, the Rialto Theater, Theatre on the Square and the Jones
Building. Each of these documents is a PDF file.
To ensure that you receive the latest
information about the RFQ/P process, including updates to the documents,
send your name and e-mail address to:
Robert.McNair-Huff@cityoftacoma.org.
This Web site will be updated with
addendums to the RFQ/P and related documents.
Application packets posted
- (Posted Feb. 16, 2006)
The three proposals submitted in January for managing the City's
performing arts facilities are included below:
The applicants are in!
- (Updated Jan. 19, 2006)
The following organizations submitted proposals by the Jan. 10 deadline
for the City of Tacoma RFP/Q for management of the performing arts
facilities:
- Village Theatre, Issaquah, WA
- Tacoma School of the Arts
Partners, Tacoma, WA
- Broadway Center for the Performing
Arts, Tacoma, WA
Questions and answers -
(Updated Dec. 16, 2005)
- Question:
Can the city
provide the winning operator with a ticket sales history for the
past seven years divided show by show and with demographics of the
audience?
Answer:
This information
is held by the Broadway Center for the Performing Arts (BCPA). A
request for sales, ticket and demographic history from the BCPA
could be made. The City does not keep records of this information.
- Question:
Can the city
provide and guarantee use of a listing of current contributors and
sponsors?
Answer:
Again, this
information is held by the BCPA. The City does not have listings of
their contributors or sponsors and therefore we could not guarantee
access and/or use of this information.
- Question:
Do you know if
the BCPA as entered into programming commitments for July 1, 2006 to
August 31, 2007, or are they planning to between now and January
10th?
Answer:
The BCPA is
working on the 2006/2007 schedule. The Pantages will be closed for
the lobby remodel this summer from June to early October. Any
contract information beyond May of 2006 would come from the BCPA.
- Question:
What are the
current commitments of the BCPA?
Answer:
The BCPA has
contracts for the remainder of the 2005/2006 season which runs to
May, 2006. They also have a separate agreement with the City for
the design and construction of the lobby remodel of the Pantages
scheduled for next summer. The BCPA is also working with the
resident arts groups for their 2006/2007 season.
New documents -
New deadline for questions
regarding RFQ/P:
RFQ/P deadline extension to Jan.
10, 2006:
Answers to questions
from the Oct. 31 walk through:
Documents:
Related information: